Documents & Information - Annual Financial Reports 2016
Community Updates
Fountain Upgrades
The Flow Way CDD will be upgrading both Fountains at the entrance beginning October 25th, and we anticipate this project to take approximately 45 days, weather permitting. During this time, both fountains will be out of service.
The plan consists of replacing all motors, plumbing, motor controller’s, electrical components, breaker box, nozzles and wave suppression and diamond bright plaster. All of the replacements are due to age related issues with the fountains, and we fully expect this capital program to last 10 years, before replacement is needed.
Joint Program for Cane Toad Removal
Cane Toad Report as of November 18, 2024 - The cane toad vendor started Flow Way CDD and HOA removal of adult and baby cane toads along with tadpole skimming on October 22nd. The first week was mainly focused on skimming tadpoles to prevent any further spreading. As of November 8th, the vendor has removed approximately 410,000 tadpole or approximately nine 5-gallon buckets full, spending roughly 19 hours of time this month skimming.
The next 3 weeks were spent removing adult and baby cane toads and skimming additional lakes for tadpoles. As of November 11th, the vendor has removed approximately 600-700 hundred golf ball sized baby toads and 350 adult toads. Problematic lakes were lakes 15b, 18,19 with late-stage tadpoles and 1,2, 20, and 21 with early-stage tadpoles. Lakes 6,8,9,11,22 and 25 all had baby toads with many adult toads that were removed. The vendor is confident that over the next couple of weeks the cane toad population will reduce, and the number of hours onsite will be limited for the next 2-3 months as lake temperatures decrease and cane toad spawning drastically holts, which is typical during this time of the year. The vendor will continue to monitor the lakes for continued growth and will have updates on ongoing progress.
October 2024 - The District and the Master Association are joining together in a program to collect cane toads. The District will institute a program to collect tadpoles from the water management system in the evening hours, and the Master HOA using traps, collect adult Cane Toads that make it to land.
We have retained the firm of Wild Things Exterminator’s for the Cane Toad Removal program. Residents will see this firm on-site, including evening hours during the collection process.
Joint Program for Cane Toad Removal Overview
_________________________________
Florida Fish and Wildlife Conservation Commission’s Statewide Nuisance Alligator Program (SNAP)
The purpose of the program is to remove nuisance alligators from the waterways of the District before they pose a problem for the Community.
This 5-year permitted program will allow the District (permit holder) to contact alligator trappers directly to initiate and control the removal of nuisance alligators. Nuisance Alligators may be considered a nuisance if it’s at least 4 feet in length and believed to pose a threat to people, pets, or property.
The best fit is a proactive solution by reporting any nuisance alligators to the District by email or phone call. Our contact information is below along with Florida Fish and Wildlife:
Richard Freeman-Asset Manager
Phone:954-644-9630
Rfreeman@cgasolutions.com
Jared Ferguson-Asset Inspector
Phone: 863-373-2725
jferguson@cgasolutions.com
James Ward-District ManagerFlorida Fish and Wildlife Hotline - 888-404-FWCC (888-404-3922). Callers can remain anonymous.
Phone: 954-658-4900
JimWard@JPWardAssociates.com
_______________________________
Pump Station Update
July 3, 2024: The
irrigation vendor will be onsite at the Esplanade Landscape Pump Station which
irrigates the residential and common areas to pull one of four pumps and
rebuild it. Rebuilding the pump will extend its lifespan, and ensure the system
has no unexpected issues in the future. This is part of an ongoing capital
program.
The work will take approximately 2-3 weeks to complete. During that time you may experience low water pressure and longer run times to ensure adequate coverage.
Thank you for your patience as we continue to improve the community.
_______________________________
Lake Bank Restoration using Geo-Tubes
Flow Way Community Development District (CDD) has undertaken a restoration program of the lake banks in the Community. Over the years, natural wave action caused by wind and fluctuating water levels has caused lake bank erosion in various portions of the 27 lakes and flow way canal. Lake Inspections were completed in 2022, so a 5-year Capital Improvement Program (CIP) could be prepared to address the non-compliant permitted slopes in a timely manner. The Stormwater Erosion Report prepared by the District Engineer provides a recommendation for lake bank restoration using geo-tubes. Each year from January though March, the District’s lake bank restoration project occurs.
Geo-tubes are sediment-filled sleeves that are used to help protect lake shores from erosion. To install a geo-tube, the lake needs to go under a pump dredging procedure. Pump dredging is performed in shallower areas to gather up all the bottom sediments and dispose them to another location or reuse the sediment to recreate a shoreline. There are three types of geo-tube bags that are used to create a new shoreline, which are a base tube, middle tube, and a sacrificial tube. The base tube will help create the new base of the shoreline, the middle tube will help create the vertical height along with setting the long steep slope at a proper ratio, and the sacrificial tube will provide a base for sod to complete the new shoreline.
The reason why shore restoration is important is because recycling soils eliminates the cost of offsite sediment disposal. Addressing the natural process of erosion and saltation will help restore the pond’s depth, slope, and grades that meet permit requirements. The process includes the use of the pond’s old materials to restore the eroded shoreline.
The final product will protect residents from potential fall accidents along the lake’s bank and promote volunteer littoral to grow and create better aesthetics for the entire community.
Click here for a Map of Lakes within the District
_________________________________
To view the Bonita Springs Emergency Water Pumping Plan click on the link below:
South Florida Water Management District Letter (SFWMD) Emergency Operational Plan Letter
Bonita Springs Pumping Operation Plan Letter (SFWMD)
Operational Plan for Emergency Pumping in the City of Bonita Springs
Links to helpful websites
- Annual Financial Report
Link to Annual Financial Report Submitted to State CFO - Auditor General
- Chapter 112 Florida Statutes
Florida Ethics Laws - Chapter 189 Florida Statutes
Special District Accountability Law - Chapter 190 Florida Statutes
Uniform Charter - Collier County Clerk Of Court
- Collier County Government
- Collier County Property Appraiser
- Collier County School Districts
- Collier County Sheriff's Office
- Collier County Supervisor of Elections
- Collier County Tax Collector
- Collier County Utilities
- Department of Community Affairs
- Department of Environmental Protection
- Department of Financial Services
- Department of Homeland Security
- Department of Transportation
- FDLE (Florida Department of Law Enforcement)
- Federal Bureau of Investigation
- Florida Commission on Ethics
- Florida Fish and Wildlife Conservation Commission
- Florida State Government
- Special District Accountability Program
State Contact for Districts and Information